Jiangsu Neusoft Intelligent Technology Co., Ltd., located in Yancheng, a coastal economic open area, is a comprehensive high-tech enterprise integrating R&D, sales, installation and maintenance. Deeply cultivating the photovoltaic energy industry, the "prestressed suspension cable photovoltaic flexible support system" independently developed by the company has been widely used and has obtained a number of patents in the photovoltaic field.
On November 26, the 300MW photovoltaic parity grid-connected project in Jiaokou County invested by TBEA New Energy was successfully connected to the grid, and it can provide an average of 40.823 million kWh of green power to the local area every year. Compared with thermal power plants with the same power, it is equivalent to saving 133,900 tons of standard coal per year (calculated based on the average standard coal consumption of 400g/kW·h), which can reduce the emission of various air pollutants each year, including reducing sulfur dioxide (S02 ) The emissions are about 11,000 tons, carbon dioxide (C02) is about 362,000 tons, nitrogen oxides (NO2) is about 990.9 tons, and soot is about 1,339 tons. The benefits of energy saving and emission reduction are significant.
The project belongs to the 2018 investment promotion project of Jiaokou County, Luliang City, Shanxi Province. The project site is located in the open-pit reclamation area of Yongxing Coal Industry in Shuitou Town. The regional soil fertility and water conservation capacity are poor, not suitable for farming, and the working conditions are complicated.
TBEA New Energy utilizes the comprehensive land utilization concept combining flat and sloped land in the coal mining reclamation area. For the first time in the construction process, it adopts the space photovoltaic flexible support independently developed and designed and produced by Jiangsu Dongsoft Intelligent Technology Co., Ltd. and the large slope and large span The distance-slope support technology effectively reduces the overall construction cost of the project, improves safety and durability, and resists damage from strong winds. According to the person in charge of the new energy project of TBEA, "The capacity of the flexible support for the same land area is about 3 times that of the conventional fixed support, which greatly improves the land utilization rate and ensures the full capacity layout of the project in the case of land shortage." .
In addition, relying on 16GW of engineering construction experience in the photovoltaic field, TBEA New Energy carried out comprehensive project planning before the start of construction, and rationally staffed it according to the construction area and professional needs, and always adhered to dynamic management during the construction process, especially in 8 In the case of continuous monthly heavy rainfall leading to delays in the construction period, the delivery team quickly responded to the decision and adopted a variety of precipitation and drainage measures to reduce the impact of natural disasters and minimize the impact of the external environment on the construction schedule.
It is understood that the 300MW photovoltaic parity grid-connected project in Jiaokou County strictly implements the material entry and inspection system and the pre-construction safety technical disclosure system, and strictly implements the project quality "three inspection" system to ensure that the construction fully understands the design intent and safety technical requirements to ensure that the project The physical quality meets the design and specification requirements. The project site arranges an engineering team with technical, business, budget, procurement, and security personnel on site to understand and solve various problems encountered in the construction process at the first time, so as to achieve the project construction progress, cost, quality, and safety goals Provides a strong organizational guarantee.
The construction and operation of this project has increased energy supply and at the same time played a role in optimizing the power supply structure of the grid. It is bound to establish a good hard environment for economic development and effectively promote Shanxi's energy revolution and county economic transformation and development.
"Becoming the leader of EPC general contracting of building photovoltaic in the country" is the direction of Jiangsu Neusoft's hard work! Adhering to the corporate spirit of "Going with Germany, sharing with peers", Jiangsu Neusoft Intelligent Technology Co., Ltd. strives to provide every user with a high-standard, high-quality one-stop photovoltaic power station solution, for "creating a green new energy world" diligent!